Dashboard

Progress
Planning (2)5%
Site Prep (1)3%
Foundation (2)5%
Framing (1)3%
MEP Rough-in (1)3%
Time

Average Slip

+4 days

Workload
Alice Johnson
Framing75%
Est. Finish

Nov 5, 2024

Slip Days

+6

Next Milestones

Roofing Complete, Windows Installed

Blockers

Lumber delivery delay

Bob Williams
Foundation90%
Est. Finish

Dec 14, 2024

Slip Days

-1

Next Milestones

Foundation Pour, Steel Erection

Blockers

None

Charlie Brown
Finishing80%
Est. Finish

Aug 10, 2024

Slip Days

+21

Next Milestones

Final Inspection

Blockers

Paint subcontractor availability, Weather delays

Alice Johnson
Electrical & Plumbing40%
Est. Finish

Feb 1, 2025

Slip Days

0

Next Milestones

HVAC Installation, Drywall Start

Blockers

None

David Green
Site Prep100%
Est. Finish

Aug 10, 2025

Slip Days

-5

Next Milestones

Foundation Excavation

Blockers

None

Bob Williams
Planning50%
Est. Finish

May 20, 2025

Slip Days

0

Next Milestones

Permit Approval, Architectural Drawings Finalized

Blockers

Zoning variance required

Alice Johnson
Drywall20%
Est. Finish

Sep 25, 2024

Slip Days

+10

Next Milestones

Taping and Mudding

Blockers

Drywall crew scheduling conflict

Charlie Brown
Curtain Wall50%
Est. Finish

Mar 1, 2025

Slip Days

0

Next Milestones

Glazing Panel Installation

Blockers

None

David Green
Platform Tiling85%
Est. Finish

Aug 28, 2024

Slip Days

-2

Next Milestones

Grouting, Signage Installation

Blockers

None

Bob Williams
MEP Rough-in60%
Est. Finish

Jun 15, 2025

Slip Days

+14

Next Milestones

Medical Gas Lines, Fire Sprinklers

Blockers

Specialty equipment vendor delay, Inspection scheduling

Alice Johnson
Landscaping30%
Est. Finish

Aug 10, 2024

Slip Days

+9

Next Milestones

Irrigation System, Planting

Blockers

Unexpected soil contamination

Charlie Brown
Abatement100%
Est. Finish

Jan 20, 2025

Slip Days

0

Next Milestones

Interior Demolition

Blockers

None

Bob Williams
Interior Finishes25%
Est. Finish

Nov 1, 2024

Slip Days

0

Next Milestones

Lobby Millwork, Guest Room Flooring

Blockers

None

David Green
Raised Flooring90%
Est. Finish

Apr 5, 2025

Slip Days

-5

Next Milestones

Server Rack Installation

Blockers

None

Alice Johnson
Precast Erection40%
Est. Finish

Oct 15, 2024

Slip Days

+14

Next Milestones

Level 3 Pour, Ramp Installation

Blockers

Precast panel fabrication error

Bob Williams
Roofing60%
Est. Finish

Nov 30, 2024

Slip Days

0

Next Milestones

Metal Siding, Dock Levellers

Blockers

None

Charlie Brown
Siding75%
Est. Finish

Sep 1, 2024

Slip Days

0

Next Milestones

Exterior Paint, Landscaping

Blockers

None

David Green
Dredging50%
Est. Finish

Feb 28, 2025

Slip Days

+13

Next Milestones

Piling Installation

Blockers

Environmental permit delay

Alice Johnson
Foundation100%
Est. Finish

Aug 25, 2025

Slip Days

-7

Next Milestones

Log Wall Erection

Blockers

None

Bob Williams
Tenant Improvements40%
Est. Finish

Aug 20, 2024

Slip Days

0

Next Milestones

Suite 201 carpet, Suite 205 final paint

Blockers

None

Charlie Brown
Spillway Concrete60%
Est. Finish

Feb 1, 2026

Slip Days

+22

Next Milestones

Gate Installation, Control Building

Blockers

Unforeseen geological conditions, High water levels

David Green
Site Utilities80%
Est. Finish

Oct 1, 2025

Slip Days

0

Next Milestones

Building Pad Prep

Blockers

None

Alice Johnson
Stage Rigging70%
Est. Finish

Sep 8, 2024

Slip Days

-2

Next Milestones

Acoustic Panels, Auditorium Seating

Blockers

None

Bob Williams
Planning80%
Est. Finish

Jul 15, 2025

Slip Days

0

Next Milestones

Final Permit Submission

Blockers

None

Charlie Brown
Structural Steel30%
Est. Finish

Mar 20, 2026

Slip Days

+19

Next Milestones

Roof Decking, Exterior Studs

Blockers

Steel fabricator backlogged

David Green
Earthwork90%
Est. Finish

Apr 1, 2025

Slip Days

0

Next Milestones

Underground Utilities

Blockers

None

Alice Johnson
Windows and Doors50%
Est. Finish

Jan 10, 2025

Slip Days

-5

Next Milestones

Exterior Cladding

Blockers

None

Bob Williams
Clean Room HVAC45%
Est. Finish

May 21, 2025

Slip Days

+20

Next Milestones

Epoxy Flooring, Fume Hoods

Blockers

Custom air handler manufacturing delay

Charlie Brown
Masonry80%
Est. Finish

Mar 20, 2025

Slip Days

0

Next Milestones

Roof Trusses

Blockers

None

Equipment Pits100%
Est. Finish

Aug 1, 2025

Slip Days

0

Next Milestones

Slab on Grade Pour

Blockers

None

Alice Johnson
Blasting20%
Est. Finish

Feb 1, 2026

Slip Days

0

Next Milestones

Crusher Installation

Blockers

None

Bob Williams
Elevator Installation90%
Est. Finish

Dec 1, 2024

Slip Days

0

Next Milestones

Lobby Finishes

Blockers

None

Charlie Brown
Lighting60%
Est. Finish

Aug 20, 2024

Slip Days

+5

Next Milestones

Final Toucups

Blockers

Custom fixture delivery delay

David Green
Field Installation40%
Est. Finish

Apr 15, 2025

Slip Days

0

Next Milestones

Bleacher Installation, Scoreboard Wiring

Blockers

None

Alice Johnson
Kitchen Equipment30%
Est. Finish

Sep 11, 2024

Slip Days

+10

Next Milestones

Health Inspection, Dining Room Finishes

Blockers

Walk-in freezer supplier issue

Bob Williams
Roofing100%
Est. Finish

Sep 28, 2024

Slip Days

-3

Next Milestones

Electrical Rough-in

Blockers

None

Charlie Brown
Access Flooring75%
Est. Finish

Feb 1, 2025

Slip Days

0

Next Milestones

Data Cabling, Security System

Blockers

None

David Green
Intricate Millwork25%
Est. Finish

Jan 5, 2025

Slip Days

+21

Next Milestones

Gold Leaf Application, Stained Glass

Blockers

Artisan availability, Material sourcing from abroad

Alice Johnson
Drywall90%
Est. Finish

Mar 1, 2025

Slip Days

0

Next Milestones

Painting, Flooring

Blockers

None

Bob Williams
Structural Concrete50%
Est. Finish

Nov 15, 2025

Slip Days

+14

Next Milestones

Post-Tensioning, Deck Pour

Blockers

Formwork crew shortage